The article emphasizes on the impact analysis using project schedule, This article is continuation of my previous article Title "PREPARING CLAIM FOR EXTENSION OF TIME (EOT)" (URL: https://www.blogger.com/blogger.g?blogID=6226101373765449612#editor/target=post;postID=2758220319089207158;onPublishedMenu=publishedposts;onClosedMenu=publishedposts;postNum=0;src=postname ). This article elaborates on how baseline schedule is helpful to identify and refer the delay events and the associated dependencies for the impact analysis. It has already been mentioned in my previous article that the approved baseline schedule is the pre-requisite for the claim preparation. The data in the Figure-1 of Article "PREPARING CLAIM FOR EXTENSION OF TIME (EOT)" can be prepared with help of project management tool. (Same Figure is referred in this article as Figure-6). . Steps to perform impact analysis using project schedule The general steps are described...