The
article provides a guideline to prepare claim of Extension
of Time (EoT) for Project. The article
also emphasize on the factors which act as pre-requisite for the preparation of
Extension of Time (EoT) claim.
A project
is a temporary endeavor undertaken to create a unique product, service or
result. The word “temporary” depicts the time bound nature of the project
requiring a start time and end time of the project to cover the project scope.
Project
managers carry out rigorous exercise along with the project team to define
project schedule as part of the plan. This schedule is used to measure and
control the schedule variance during the rest of the phases of project. However
many projects do not complete within the agreed upon timelines. There are
various reasons of the delays in the project
The
articles focus on the identification of delays and impact caused by the
dependencies in the agreed upon project timelines. If these dependencies are
not resolved in timely manner, this will impact the successor activities
henceforth rest of the work. Therefore the delay in the resolution of
dependencies results in the delay in the overall project. The impact of the
delays is severe when the critical path activities are subject to effect.
Project
manager keep monitoring the risks registers and project dependencies to
evaluate the impacts. Any deviation of time brings impact on projects. Even the
stakeholders may have to compromise on the scope to meet the deadlines, or
incur cost due to crashing and fast tracking. Even to extend the timelines.
There are
certain reasons of extension of time. If the extension of time is due to the
new scope induction through change management, it is simply a forecasting of
the effort required based on the scope of change.
This
article focus on preparation of claim for the EoT critical to avoid the
penalties and sometimes helpful to impose the penalties to the contractor.
The Impact
analysis of the delays due to the dependencies is explained in this paper. And
how the impact analysis can be referred in the claim to make it rationale and
convincing with the evidence of the facts causing delays. An example of project
schedule is provided to illustrate the steps required in primavera to perform
impact analysis for the interim claim of EoT.
CONDUCT PROJECT DELAY ANALYSIS AND
PREPARE EXTENSION OF TIME (EOT) CLAIM
Many
projects get delayed due to various reasons. Specially, the high value and high
risk projects for large enterprise have the greater tendency to run of time due
to complexity of integrated environments resulting in internal and external
dependencies. Usually these projects are fixed cost projects with waterfall
methodology achieved though bidding process.
In the
fixed cost projects any delays may cause severe financial impacts if not properly
handled. Even the delays incurred in the
project can trigger the late delivery charges due to the delay in project
completion.
Project
manager therefore has to play a significant role in the identification of the
delays but also the reason of the delays to calculate time of extension and
rationale of the delay.
The below
mentioned items serve as the pre-requisite to submission of Extension of Time
(EoT) claims.
1. SETTING UP THE PRE-REQUISITES
1.1. PREPARE BASELINE PROJECT SCHEDULE
This
article does not cover the process to prepare the project schedule in this
article. The PMI standards are very well defined to understand the mechanism to
create project schedule. It is urged that project schedule preparation is one
of the keystones for successful project management. The project managers should
define detailed work break down structure will all the tasks, milestones and
dependencies. Project managers should focus on the identification of
dependencies and risks both internal and external Project schedule with clearly
defined dependencies enables project managers to monitor and control the
schedule.
1.
Dependencies
While
defining dependencies project team should think of all the possible
dependencies of Engineer, or third parties that are employed by the Engineer to
carry out Employer’s portfolio as well as programme. The project manager must
ensure that the dependencies including discretionary and mandatory are properly
identified. These third party dependencies may impact to the project schedule at
the later stage thus drag the project completion dates from initially planned
project completion date.
The
importance of defining dependencies within the project at the earliest stages
provides multifaceted benefits to the project team; they help all the
stakeholders to understand the limitations and constraints that may impede the
project timelines, also each stakeholder agrees to what is expected of them, In
addition to this the project progress monitoring brings transparency to the
timelines variation along with the root cause. Couple of examples include:
Provision
of Approval of design by the Engineer to initiate the installation and
configurations
2.
Data Date
For the
initial version of project schedule cutoff date is set to Project Commencement
date.
.
Very simple
example of schedule is provided to understand the theme of the delay
calculation due to delay factor that have impeded other activities due to the
dependency as set out in the baseline schedule.
1.2. SEEK APPROVAL OF BASELINE PROJECT SCHEDULE
Once a
project schedule baseline version is prepared. Project manager must seek the
formal approval of the baseline project schedule. This project schedule will
serve baseline to measure any variance of time with respect to the actual
dates. The approval of the baseline project
schedule will be used for future reference.
1.3. PREPARE AND DISSEMINATE PROJECT PROGRESS REPORT
Project
manager prepared and disseminates reports after agreed upon time period. In
each report project schedule percentage completion is marked along with the
updated Cut Off date. The project schedule may be referred as a Programme.
The Program
serves the key to identify any time variances, and possible impacts the delayed
activities. Project manager should keep
list of risks, dependencies in the status report.
1.4. SERVE NOTICES
Project
manager should proactively initiate stakeholders, project sponsors and client
organizations. The notices with the possible delays should be highlighted and
officially communicated in case of open ended dependencies that have caused
delays as compared to the baseline version.
The
baseline schedule, Program and evidences like letters must support the
rationale of serving notices. Furthermore, these notices are the pre-requisites
to the Extension of Time claim.
There may
be several notices served for different issues or even multiple notices may be
served for critical delays.
1.5. PREPARE CLAIM FOR EXTENSION OF TIME (EOT) CLAIM
The
pre-requisites in section 2 have been clearly worked out along with the passage
of time.
The
aforementioned items are all required to submit the claim for extension of
time. The delays are identified. Following are the main areas to be addressed
in the Extension of Time (EoT) claim:
1.5.1. INTRODUCTION AND BACKGROUND
In this
section you may provide the details that comprise of the following information
in order to elaborate the context and rationale for the claim to be submitted:
1.
Provide brief overview of the project with aim and
background.
2.
Specify the commencement and awarding of the contract
by the Engineer.
3.
Explain the purpose of the Claim document
4.
Provide evidence of the submission of baseline
schedule to the Engineer
5.
Provide evidence of the approval of the baseline
schedule by the Engineer.
1.5.2. BASIS OF
ENTITLEMENT OF EXTENSION OF TIME
In this
section provide you may Refer to the clauses of the contract that entitles
contractor to apply for the extension of time. This will bring you in a
negotiation position. Usually the high risk high value project contracts are
quite extensive and comprise of such provisions of entitlement to claim an
Extension of Time. For example:
“The Contractor may claim an extension of
the Time for Completion….”
a)
the
failure of the Employer to fulfil any of his obligations under the Contract,
b)
delay
by any other contractor engaged by the Employer,
1.5.3. DETAILS OF DELAY IN EVENTS
In this
section specify complete scenario of delays, correspondence for further
necessary action, served notices, and impact of any feedback on the resolution.
And the status of the resolution on the current stage.
As briefed
in section 2, project manager prior to sending EoT claim must have served
multiple notices based on the delayed activities of the project. All such
references will help you make your claim furbished with evidences for
consideration by the Engineer
In our example,
the main delay event is the lack of provision of test server by the Engineer
which has stalled activities comprising of deployment of application on the
test and henceforth the P2P testing of Module A, B and C are stalled till the
dependencies are resolved by the Engineer.
In this
scenario, it is expected from the project manager that time to time notices
must have been served with the purpose to request the provision of the test
server.
1.5.4. CALCULATION OF DELAYS
This is the
most important step for the delays analysis and quantify the new completion
date to claim the extension of time for project completion. There may be a
situation where couple of delaying dependencies which are closed and rest of
them are still open.
For the
closed dependencies, you have the actual date that you can feed in the project
schedule to calculate the delay impact, However for the dependence that are not
closed, you need to mark a assumed date of completion (may be current date) for
evaluating impact on the impacted project activities to start their normal
course of action.
It is
important to mention here that if the delay analysis is calculated based on the
assumed date, there is a chance that the dependency may not be closed even on
the assumed date. Therefore it would be better to state that the claim is
interim.
In the
example, the main delay event is the lack of provision of test server by the Engineer
which has stalled activities comprising of deployment of application on the
test and henceforth the P2P testing of Module A, B and C are stalled till the
dependencies are resolved by the Engineer.
It is
important to mention here that the tasks must be on the critical task so they
do not have float.
Sr.#
|
Activity Head
|
Activity ID
|
Start Date
(Baseline 1)
|
Anticipated Start Date
|
Project Finish Date
(Baseline 1)
|
Impact on Project Finish Date
|
Variance
(days)
|
1
|
Application P2P Testing
|
P2P1010
|
19 Mar 18
|
15 May 18
|
6 May 18
|
4 Jun 18
|
29
|
2
|
P2P Test of Module B
|
P2P1020
|
26 Mar 18
|
15 May 18
|
6 May 18
|
28 May 18
|
22
|
3
|
Application P2P Testing
|
P2P1030
|
2 Apr 18
|
15 May 18
|
6 May 18
|
21 May 18
|
15
|
The above
table depicts the Impact analysis based on the activities referred from
baseline project schedule. The
cumulative effect of the overall delay events results in a delay for the
project in number of days as causing of the shift from baseline completion date
to new completion date.
My article "Performing Impact Analysis for Extension of Time(EoT) Using Project Schedule"
(http://naveedsrana.blogspot.com/2018/07/performing-impact-analysis-for.html ) elaborates on how the project schedule can be used to perform impact analysis.
My article "Performing Impact Analysis for Extension of Time(EoT) Using Project Schedule"
(http://naveedsrana.blogspot.com/2018/07/performing-impact-analysis-for.html ) elaborates on how the project schedule can be used to perform impact analysis.
Comments
Post a Comment